| For PTFE, 25% Glass Filled Slide Plates:
Prior to Welding: Locate the slide plate base in the appropriate position on the existing steel surface. Place a protective covering on the PTFE, 25% glass filled. Where seal welding is not required, follow the diagram shown which indicates 1/8 inch thick fillet weld, 1 inch long every 4 inches around entire perimeter of the base. For welding, use GMAW 0.035 wire or SMAW 3/32 inch stick.
Where full seal welding is required, use a similar pattern of welding until a full weld is obtained. This method will prevent damage to the PTFE, 25% glass filled. (A full weld will help prevent seepage of water between the slide bearing plate and the support structure.) Avoid overheating, which may destroy the bonding of the PTFE, 25% glass filled to the base plate.
Installation in Concrete: Secure the top and bottom elements together with paper adhesive tape. Then attach the bottom element anchor bolts with wire to the form. After the bottom pour is made, repeat on top element. During the first expansive cycle, the tape will break.
For Graphite and Bronzphite Plates - see link below: |
Related Articles
Are there improper ways to install PTFE slide plates that would cause them to debond, degrade, or crunch?
Added on Thu, Nov 3, 2011
What is the use of a slide plate?
Added on Wed, Dec 1, 2010
How long are each of the slide plate elements designed to last for and do they require much maintenance and replacement?
Added on Thu, Nov 3, 2011
Why are slide plates sometimes required in a piping system?
Added on Thu, Feb 17, 2011
What are reasons why the PTFE or Graphite pads peel off the backing plates?
Added on Thu, Nov 3, 2011
|